How the project runs

From the plot check to the keys, the project follows one route. At every stage it is clear what is happening, what you receive and which document confirms it.

Construction takes 4 months; the countdown starts once the starting conditions are met (plot readiness, site access, approved specification, permitting conditions). The contract states the period in calendar days.

  1. Preliminary plot check

    What happens

    We check land designation, dimensions, access, terrain and available utilities using the cadastral code and photos.

    What you receive

    A preliminary conclusion on the plot's compatibility with ALAZANI 130.

    A written check summaryCarried out before any contract is signed
  2. Topography and geology

    What happens

    A survey and soil investigation define the house placement and the foundation type.

    What you receive

    A topographic plan and a geology report.

    Surveyors' reportsTerms are fixed before the work starts
  3. Siting the design

    What happens

    The architect places the house on the plot: orientation, setbacks, entrance, terrace, utility points.

    What you receive

    A placement scheme for your plot.

    Siting master planTerms are fixed by the contract
  4. Scope approval and contract

    What happens

    We fix the completion level — BASE or BASE + FINISH, the selected modules and the full specification.

    What you receive

    A contract with a locked price and scope of works.

    The contract and specification annexesFirst scheduled payment — after signing
  5. Building permit

    What happens

    We prepare and submit the documents and manage the permit process.

    What you receive

    A building permit for the house.

    Permit documentationPer the payment schedule in the contract
  6. Foundations and structure

    What happens

    Groundworks, reinforcement, concreting, the load-bearing frame. Concealed works are documented with photo reports.

    What you receive

    The completed structure of the house.

    Concealed-works reports, rebar photo recordsStage payment per the contract schedule
  7. Envelope, facade and roof

    What happens

    External walls, insulation, roof, windows, external doors, facade.

    What you receive

    A closed, warm envelope protected from the weather.

    Thermal-envelope completion reportStage payment per the contract schedule
  8. Services and internal works

    What happens

    Electrics, plumbing, heating, air-conditioning preparation, partitions, plaster, screed.

    What you receive

    The house at BASE completion — ready for final finishes.

    Services test reportsStage payment per the contract schedule
  9. FINISH, if selected

    What happens

    Finished surfaces, doors, sanitary ware, electrical fittings, lighting, the kitchen and appliances per specification.

    What you receive

    The house with final finishes and a ready kitchen.

    Finishing-works acceptance reportsStage payment per the contract schedule
  10. Quality check and handover

    What happens

    The final checklist, system tests, cleaning, documentation handover.

    What you receive

    Keys, the warranty passport and the full document set.

    Handover act, warranty passportFinal payment per the contract schedule